Cape’s T955 Trencher and SPD-150 Padding Machine made light work of a Gas Pipeline Project in the Goldfields.

by on 6th February 2018

The Cape Team completed 2.5km of trenching with 600 cubic meters of pipe bedding and backfilling to allow the installation of a 150mm steel gas main at Dacian Gold’s Mt Morgan Mine 20km West of Laverton.

The trenching was completed in 3 days whilst the backfilling was completed in 2 days which was a cost effective and efficient solution for our client.

Another great example of our CapeAbility.

 